In my last post, the Case Type was named after the event that started the work, and the fix was to widen it to the whole transaction. This post is about the opposite pressure. Once a Case Type is the right size, everybody wants to split it.
The requests arrive in the first week and they all sound reasonable. We have three products, so three Case Types. We operate in two regions with different rules, so two more. The commercial team handles things differently from the retail team. Finance wants to report on each line separately. Blueprint, asked for six Case Types, will generate six, each with a plausible lifecycle, and the design will look thorough.
It isn’t thorough. It’s the same work drawn six times. The Solution Designer’s job here is to ask one question of every proposed split: does this variation change the work, or only the words around it?
A baseline Case Type is the default. A specialized Case Type is warranted only when a variation materially changes the structure or governance of the work: a substantially different lifecycle, different core data requirements, or distinct mandated obligations. Products, regions, teams and reporting needs are variation the same Case Type can carry.
Twelve licenses, twelve Case Types
A city licensing office has been live on its new permits application for eight months. It issues a dozen kinds of business license: food service, liquor, street vending, taxi operation, construction, signage, and so on. Each has its own Case Type, because each has its own application form, its own fee schedule and its own inspection checklist, and when the Blueprint was generated that seemed the obvious way to keep them straight.
The director of licensing asks a simple question: how long does it take, on average, to issue a license, and where do applications get stuck? The team cannot answer it in one report. The twelve Case Types have drifted. Three of them call the first Stage Submitted and the rest call it Received. Two have an Inspection Stage, four have inspection as a Process inside Review, and one has it in both places after a fix. A change to how fee payments are confirmed had to be made twelve times, and was made eleven.
The Solution Designer brought in to help starts by walking the twelve lifecycles side by side. They are the same lifecycle. An application is received, checked for completeness, reviewed against the rules for that license, inspected where the license type requires it, decided, and issued or refused. What differs between them is which form the applicant fills in, which rules apply at review, whether an inspection is needed, and what the fee is. Those are differences in configuration, business rules and conditional Processes. None of them changes the structure of the work or who governs it.
The redesign is one Business License Case Type. License type is a field. The form, the fee, the applicable rules and whether the inspection Process runs are all driven by it. The director gets one report. The next change to fee confirmation is made once.
Nothing about the twelve licenses has been flattened. They are still twelve licenses. They were never twelve kinds of work.
The one that genuinely is different
A health plan is designing prior authorization in Blueprint: the process by which a provider asks the plan to approve a treatment before it is delivered. Having heard the licensing story, the utilization management lead is determined not to over-split. One Prior Authorization Case Type, with the type of service as a field. Inpatient, outpatient, pharmacy, durable equipment: all the same work.
The Solution Designer agrees with the instinct and then asks the test questions anyway, one variation at a time.
Service type: same lifecycle, same core data, same obligations. A field.
State or region: different rules at review, decided by the rules engine. Configuration.
Which clinical team reviews it: routing.
Expedited requests: here the answer changes. When a provider marks a request as urgent because a delay could seriously harm the patient, the plan is under a mandated turnaround measured in hours rather than days, with a mandated escalation if the deadline is at risk and a required clinical reviewer for any denial. The request skips the completeness-check queue, goes straight to clinical review, and cannot be pended for more information in the way a standard request can. The lifecycle is substantially different, and the obligations the plan is held to are distinct and non-negotiable.
That is a specialized Case Type. Not because urgent requests matter more, although they do, and not because a different team handles them, although it does, but because the structure of the work and the governance around it are materially different. Expedited Prior Authorization becomes its own Case Type, sharing the baseline’s data and rules where they fit and departing from it where they don’t.
The lead’s instinct was right about three of the four variations. The test is what caught the fourth.
Three things that pass the test, and four that don’t
The two scenarios came out differently because the test came out differently, and the test has exactly three ways to pass.
A substantially different lifecycle. Not a Stage with a different name, and not a Process that runs for one variant and not another. A route through the work that stakeholders would recognize as a different journey, with different milestones.
Different core data requirements. Not extra fields for one product. A materially different set of information the Case exists to capture and act on.
Distinct mandated obligations. A separate set of SLA or compliance commitments the organization is held to for that variation, with their own consequences for failure.
Against those, the four variations that arrive most often and never pass on their own:
Different products. Product is a field. The forms, fees and rules it drives are configuration.
Jurisdiction-specific rules. Rules differ by region; the work the rules govern does not. That is what a rules engine is for.
Different routing or teams. Who does the work is a routing decision, and routing changes when the organization changes. A Case Type should survive a reorganization.
Reporting requirements. Reporting slices a single Case Type by any field it carries. Splitting the Case Type to get a report is the one move that makes the report harder, as the licensing office found out.
The tempting objection is the one every stakeholder makes about their own area: ours really is different. It usually is different, to the people doing it. The question the test asks is narrower. Different in what the work is, or different in how it is described? Importance, visibility and team pride are all real, and none of them is on the list.
Two honest notes about the source. First, the Academy material argues this from structure and governance, not from maintenance cost. The licensing office’s eleven-out-of-twelve fix is a consequence you will recognize, but the principle stands without it: twelve Case Types misrepresented one kind of work. Second, this decision comes after the Case boundary is drawn correctly (the previous post) and before the separate question of whether related work should become a Child Case, which has its own test and its own post.
And a note about Blueprint. It generates what it is asked for, and a description that lists products or regions as distinct things will tend to produce a Case Type for each. Reviewing a generated design for over-specialization is one of the first things to do, because every specialized Case Type that shouldn’t exist brings a lifecycle, a set of Stages and a set of Personas that shouldn’t exist either.
Final thought
The next time someone tells you their variation needs its own Case Type, don’t argue. Ask them to describe the journey. If they describe the same Stages with different words, it’s a field. If they describe different Stages, different information, or a different set of promises the organization has to keep, you may have found one of the three.
And keep a running count. In most engagements, the number of specialized Case Types that survive the test is smaller than the number of products, smaller than the number of regions, and far smaller than the number of teams. That isn’t a failure of imagination. It’s what one kind of work looks like.